Page 254 - TSMC 2018 Annual Report
P. 254
Company Name
Types of Property
Transaction Date
Payment Term Counter-party
Nature of Relationships
Price Reference
Purpose of Other
TSMC
Fab Fab Fab Fab Fab Fab Fab Fab Fab Fab Fab
November 10, 2017 to May 24, 2018
$ 305,783 948,048 1,724,550 7,219,028 2,457,695 305,566 525,172 1,744,533 315,886 2,564,709 5,387,421
Monthly settlement by DESICCANT
the construction TECHNOLOGY CO., progress and LTD.
acceptance
- - - - - - - - - - -
N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Price comparison and price
Manufacturing None purpose
November 13, 2017 to August 13, 2018
Monthly settlement by Chen Yuan International Co., the construction Ltd
progress and
acceptance
Price comparison and price
Manufacturing None purpose
November 14, 2017 to April 16, 2018
Monthly settlement by PAN ASIA Corp. the construction
progress and
acceptance
Price comparison and price
Manufacturing None purpose
December 5, 2017 to July 31, 2018
Monthly settlement by UNITED INTEGRATED the construction SERVICES CO., LTD. progress and
acceptance
Price comparison and price
Manufacturing None purpose
December 13, 2017 to July 23, 2018
Monthly settlement by Taiwan Puritic Corp. the construction
progress and
acceptance
Price comparison and price
Manufacturing None purpose
December 14, 2017 to May 23, 2018
Monthly settlement by WHOLETECH SYSTEM the construction HITECH LIMITED progress and
acceptance
Price comparison and price
Manufacturing None purpose
December 26, 2017 to February 13, 2018
Monthly settlement by ABB Ltd. the construction
progress and
acceptance
Price comparison and price
Manufacturing None purpose
January 4, 2018 to April 16, 2018
Monthly settlement by KEDGE Construction Co., the construction Ltd.
progress and
acceptance
Price comparison and price
Manufacturing None purpose
January 5, 2018 to April 16, 2018
Monthly settlement by Shihlin Electric &
the construction Engineering Corp. Tainan progress and Branch
acceptance
Price comparison and price
Manufacturing None purpose
February 5, 2018 to July 31, 2018
Monthly settlement by L&K ENGINEERING the construction CO.,LTD.
progress and
acceptance
Price comparison and price
Manufacturing None purpose
February 6, 2018 to August 13, 2018
Monthly settlement by Fu Tsu Construction Co., the construction Ltd.
progress and
acceptance
Price comparison and price
Manufacturing None purpose
Transaction Amount (Foreign Currencies in Thousands)
Prior Transaction of Related Counter-party
- 107 -
Owner
Relationships
Transfer Date
Amount
Acquisition
Terms
negotiation
negotiation
negotiation
negotiation
negotiation
negotiation
negotiation
negotiation
negotiation
negotiation
negotiation
(Continued)